An 811 ticket is the notice, not the clearance
← INSIGHTS
Excavation · 2026-11-14

An 811 ticket is the notice, not the clearance

The two full business days the law actually counts, why the positive response is the half everybody skips, what to do when the code and the ground disagree, and the twenty-four inches where the machine stops.
Every fence post, every paver base, every drain line that leaves a house goes into ground somebody else owns a piece of. Florida handles that with chapter 556 of the statutes — the Underground Facility Damage Prevention and Safety Act — and almost all of what it asks of an excavator is one notice, free, two days ahead. The part that gets skipped is not the notice. It is what comes back from it. A ticket number proves you gave notice; it does not say the site is clear, and since 2010 reading the answer has been the excavator’s own legal duty, not a courtesy the utility does. Everything below is the statute and Sunshine 811’s published guidance, cited by section, because the only part of a document like this worth having is the part somebody else can check.
Two full business days, and the law counts them — not the calendar
01
Two full business days, and the law counts them — not the calendar
The notice goes in not less than 2 full business days before any excavation or demolition that is not beneath the waters of the state, and not less than 10 full business days if it is. That is s. 556.105(1)(a), and the two words that do the work in it are full and business. The act defines business days as Monday through Friday with a list of holidays taken out, so a ticket called in on a Thursday afternoon does not clear a Saturday and usually does not clear the Monday either: Friday and Monday are the two full days and Tuesday is the first morning. A holiday inside the span pushes it again. Everybody remembers the number two. The number is the easy part.
The ticket is the notice. The positive response is the answer
02
The ticket is the notice. The positive response is the answer
Once the system passes the notice along, each member operator has to give a positive response back to the system within those same two full business days, saying what it did about its own facility — s. 556.105(9)(a). That is a separate record from the ticket, it arrives from each utility separately, and it is the only thing that actually states whether anybody’s line is in the way. Sunshine 811 publishes two ways to read it, by ticket and phone number on its site or by calling 811 and choosing option 5, and says plainly that its own agents cannot read it to you. Work can start once every operator has answered Clear/No Conflict or Marked, or once the two full business days have run out — whichever comes first.
When the code and the ground disagree, the ground wins
03
When the code and the ground disagree, the ground wins
This is the whole reason to read the responses instead of just waiting out the clock. A code that says marked, on a site where that utility’s color is nowhere on the ground. A code that says clear, thirty feet from that same utility’s pedestal, amplifier or cabinet. An unmarked code that came with an instruction for you that nobody carried out. Each of those is a mismatch between a record and a site, and a mismatch is not something to dig through — it is a second notice through 811, or a call straight to that operator. Sunshine 811 puts it the same way: compare the marks against the codes on site, and when they do not match, contact the member directly. Ten minutes against a severed service line, and under s. 556.107 a noncriminal infraction sitting on top of it.
Gas and fuel put an extra call on you, not on them
04
Gas and fuel put an extra call on you, not on them
A high-priority subsurface installation, in s. 556.103(8), is a gas transmission or distribution pipeline, or a line carrying gasoline, jet fuel, another refined petroleum product, or a hazardous or highly volatile liquid such as anhydrous ammonia, where its operator deems it critical. If the work falls within 15 feet of one and that operator tells you in time that it is there, s. 556.116(1) turns the duty around: the excavator then has to notify that operator of the planned start date and time before breaking ground. Not the ticket, not 811 — that operator, directly. If the operator does not give timely notice, you may go ahead after the waiting period without making the call. It is the step a working crew misses most often, precisely because everything else in the process happens without them.
What the colors mean, and the white one is yours
05
What the colors mean, and the white one is yours
Sunshine 811 publishes the marking colors and they do not vary by county: red is power, yellow is gas, orange is communications — internet, cable, fiber — blue is potable water, purple is reclaimed water, green is sewer. They arrive as paint, as flags, or as both. The one color on the job that is not a utility’s is white, and it belongs to whoever is digging: the act defines premark as delineating the general scope of the excavation on the surface of the ground in white paint, white stakes or similar white markings, and where a ticket cannot describe the site with enough particularity for the operator to find it, premarking is what is owed before a locator has to come out at all.
Twenty-four inches, and then the marks expire
06
Twenty-four inches, and then the marks expire
The tolerance zone in s. 556.103(15) is 24 inches from the outer edge of either side of the exterior surface of a marked facility, so one painted line carries a protected band roughly four feet wide plus whatever the line itself measures. Inside it s. 556.105(5)(c) asks for increased caution, and any use of mechanized equipment within the zone has to be supervised by the excavator — Sunshine 811 recommends digging that part by hand, and says the thing the paint cannot: locators do not give depth, so something correctly marked can still be inches below the grass. None of it is permanent either. Ticket information is good for 30 calendar days and non-permanent markings for the same, and under s. 556.105(11) if the marks go missing or stop being visible, before the work or during it, the excavator stops and has them remarked.
None of this is specialized knowledge and the notice itself is free, which is exactly why it gets filed under paperwork and skipped at the end. A fence is the clearest case on a residential lot — the holes go down on a property line, which is where services tend to cross — and a paver base is the second, because that excavation is wide even where it is shallow. On our own scopes the locate request goes in before anybody excavates, the site gets premarked in white, and the responses get read against what is actually painted on the ground, which is the step this whole article is about. What is not ours is worth saying too: we are not the locator and we mark nobody’s facility, we work as general services or as a subcontractor to a licensed GC, and any scope that requires a license goes to a subcontractor licensed for that trade. If somebody is about to dig on your property, the question worth asking is not whether they called 811. It is what the responses came back saying.