CHALLENGE
The center could not close. Patients, staff and imaging equipment stayed in the building every day of the work.
SOLUTION
Phased zone by zone around the appointment book: reception and waiting first, then exam corridors and sub-waiting rooms, each zone cleaned and handed back before the next one opened. Transitions and wall base rebuilt as we went.
RESULT
New flooring throughout, no canceled appointments, no equipment moved twice. One week.